Commissioning an Injection Moulding MTC: The 7-Step Setup Checklist
November 18,2026
The First Week Decides the Next Three Years
Most mold temperature controller complaints that reach us as factory support tickets were created on day one of installation — an undersized heater, a circuit with two dead legs, a sensor in the wrong place. A disciplined installation is worth more than any specification upgrade later.
This is the checklist we work through before commissioning any unit.
Before the Machine Arrives
- Electrical supply — confirm voltage, phase and frequency match the nameplate. 380 V / 3P / 50 Hz is standard for most export markets; 220 V single phase is available for small units.
- Supply capacity — check the transformer can handle the heater load with the rest of the plant, especially if several MTCs start together.
- Floor area and service clearance — leave room to pull the pump and heater for maintenance, not just to install the cabinet.
- Ambient temperature — above 40 °C ambient, derate capacity and confirm the cooling approach still works.
- Water quality — for water type units, check hardness and iron content. Scaling in the heater cuts efficiency badly.
Pipework and Circuit Design
1. Insulation Is Not Optional
Insulate every pipe between the MTC and the mould, including the mould itself. An uninsulated 10 m run can lose more heat than the mould absorbs, and the controller will spend its life fighting the loss.
2. Balance the Flow
For multi-cavity moulds, flow must reach every cavity evenly. The classic mistake is a single inlet feeding a long runner, so the last cavity runs several degrees cooler. Use a properly sized manifold or a balancing circuit.
3. Avoid Dead Legs
A dead leg is a length of pipe with no flow. It collects stagnant oil or water that degrades, then blocks flow when it finally breaks loose. Eliminate them from the layout.
4. Fit Isolation Valves and a Filter
Fit a ball valve at the MTC outlet, one at the mould inlet and return, and a strainer or magnetic filter on the suction side of the pump. Without them, a failed seal or a piece of debris becomes a full teardown.
5. Use the Right Pipe Material
For oil circuits above 150 °C, use stainless steel or high-temperature rated fittings. Standard galvanised or brass fittings will fail.
Electrical Installation
- Earth the cabinet properly and verify with a meter before energising.
- Wire the flow switch, level switch and over-temperature cut-out into the control circuit — do not bypass them.
- Confirm the circulation pump direction: check that flow is actually present at the mould before closing the loop.
- Set the over-temperature protection to a sensible value above the operating temperature but below the flash point of the oil.
- Record the motor and heater currents at first run so you have a baseline.
Commissioning Checklist
- Fill and bleed the circuit. Fill the tank, run the pump and bleed air from the highest point of the circuit until flow is steady and free of noise.
- Verify flow at the mould. Do not trust the pump reading. Check at the mould inlet with a flow meter or by temperature differential across the coil.
- Heat up and check stability. Bring the setpoint up gradually. Watch for overshoot — it indicates poor circulation or air in the system.
- Set the control sensor. If the controller has both a tank sensor and a mould sensor, the mould sensor must be the controlling input.
- Tune the PID. Start conservative and adjust. Record the final values.
- Run a full production cycle and check mould temperature across all cavities, not just at the sensor position.
- Document everything — flow rate, setpoints, PID values, over-temperature setting and heater current.
Common Installation Errors
| Error | Symptom | Fix |
| Undersized heater | Temperature falls during the run, recovers between shots | Re-size heater capacity to the actual circuit load |
| Air trapped in the circuit | Erratic control, noise, pump cavitation | Bleed the system properly at commissioning |
| Sensor in the tank only | Mould runs hot or cold regardless of setpoint | Install a mould or mould-inlet sensor |
| No pipe insulation | High energy use, unstable temperature | Insulate all runs and the mould |
| Unbalanced multi-cavity flow | Different cavity temperatures, inconsistent parts | Rebalance with a manifold |
| No flow switch protection | Heater runs with no flow — a fast heater failure | Wire the flow switch into the heater enable circuit |
Handover Checklist
- Operating manual for the specific unit.
- Heater and pump spare part numbers.
- Recommended oil type and quantity for oil units, and water quality specification for water units.
- Recommended maintenance intervals.
- Your commissioning record with flow rate, setpoints and PID values.
Conclusion
A careful installation is the difference between a controller that holds temperature and one that never quite does. Zillion MTCs are supplied with commissioning guidance, and our water type range is available in CE and SGS certified versions — see the SGS and CE certified temperature controller note. If you want an installation review before commissioning, send us your circuit drawing and we will check it.