ZL-20T 20 Ton Industrial FRP Counter Flow Cooling Tower - HVAC EPC Contractor
The ZL-20T integrates into HVAC chiller condenser water loops as the heat rejection component:
Loop configuration: Closed-loop chilled water from chiller evaporator to building air handlers, with condenser water pumped from chiller to ZL-20T cooling tower and back. Typical flow 16 m³/h matches the design.
Piping: 50 mm (2") flanged connections at ZL-20T inlet and outlet. Schedule 40 steel or PVC piping typical for condenser water. Pipe sizing should maintain water velocity 1.5-2.5 m/s for optimal heat transfer.
Water treatment: Standard closed-loop HVAC treatment (corrosion inhibitor + biocide) maintains clean condenser water and prevents biological fouling in the ZL-20T fill media.
Control integration: Optional BMS integration enables chiller staging based on ZL-20T leaving water temperature. Typical control setpoint: 32°C leaving water activates additional chillers.
The ZL-20T fan motor requires standard industrial power:
Voltage: 380V 3-phase 50Hz (also compatible with 400V, 415V, 440V at 60Hz with derating).
Motor specification: 0.55 kW (0.75 HP), 1440 rpm synchronous speed, IE3 efficiency class, IP55 enclosure, Class F insulation.
Full load current: 1.5 A at 380V. Cable sizing: 3 × 1.5 mm² PVC copper for runs under 50m, 3 × 2.5 mm² for runs over 50m to limit voltage drop below 3%.
Motor protection: Thermal overload relay setting 1.5 A (1.0 × FLA). Phase failure relay required for installations with unstable 3-phase supply (common in rural or generator-backed operations).
VFD compatibility: 0.75 kW VFD enables variable speed operation for partial load energy savings. 30-60 Hz speed range provides 4:1 turndown ratio.
ZL-20T foundation design per installation:
Concrete pad: 600 x 600 x 100 mm reinforced concrete pad at installation location. 200 kg/m² distributed load capacity.
Rooftop installations: Verify roof structural capacity for 300 kg operating weight + 100 kg dynamic load (wind, seismic). Most industrial buildings support ZL-20T rooftop installation.
Steel platform mounting: For elevated installations, hot-dip galvanized steel platform with vibration isolators recommended.
Anchoring: 4 × M12 expansion bolts per ZL-20T base flange. Torque to 60 Nm. Wind load design per local code (typically 0.5-1.0 kPa).
Piping support: First elbow support within 1m of ZL-20T connection to prevent nozzle stress.
Standard ZL-20T HVAC integration project timeline:
Day 1-3: Delivery and positioning at installation site. Crane or forklift required for rooftop installations (300 kg operating weight).
Day 4-5: Foundation preparation (concrete curing if new pad). Electrical and piping rough-in.
Day 6-7: Final piping and electrical connections. Tower anchoring. Motor rotation direction verification.
Day 8: Initial fill and leak test. Power-on commissioning. Performance verification at design conditions.
Day 9-10: Operator training and handover documentation delivery. Punch list closeout.
Total project duration: 10 working days from delivery to commissioning for typical retrofit installation. New construction integrates into broader HVAC system commissioning.
The ZL-20T contributes to LEED and other green building certification through documented performance:
EAc Optimize Energy Performance: 0.55 kW fan motor with IE3 efficiency class contributes to chiller energy savings. Calculated kW/ton (0.0275) below ASHRAE 90.1 baseline for cooling towers (0.04 kW/ton).
EAp Minimum Energy Performance: Fan motor efficiency documentation supports M&V (Measurement and Verification) requirements.
Water efficiency (WEc): 10 L/h drift loss below ASHRAE 188 baseline (15 L/h for equivalent capacity) supports cooling tower water consumption credits.
Material credits (MRc): FRP shell contains recycled content option. Documentation package available for LEED submittal.
For projects pursuing LEED v4 or BREEAM certification, the ZL-20T submittal package includes all required documentation templates.
The standard ZL-20T submittal package for EPC contractor design approval:
Drawing package: General arrangement, foundation plan, piping connection details, electrical wiring diagram, control schematic.
Specification sheet: Performance data, materials of construction, motor specification, certifications list.
Compliance documentation: CE Declaration of Conformity, ISO 9001:2015 quality system certification, material test certificates.
Calculation backup: Heat duty calculation, fan performance curve, head loss curve, electrical load calculation.
Installation manual: Foundation requirements, piping and electrical connections, commissioning procedure.
Submittal package format matches standard project specification requirements and includes editable CAD drawings for design team integration.
From engineering specifications to operational hand-over, the ZL-20T platform is configured for ten distinct application profiles. Explore the other nine below: